Road Construction Projects

DOT Construction Projects

Click the above image for 511 Wisconsin Construction Projects (Northwest Region)

2020 Sawyer County Construction Projects

County Road B

(River Road to Hemlock Haven Road)

4.6 miles

Project consists of 2” hot mix overlay, placement of shoulder gravel, and pavement marking.

County Road H

(Ashegon Fire Lane – Blueberry Lake Road)

2.3 miles

Project consists of pulverizing the existing pavement, replacing all cross drain culvert pipes, placement of 3.5 inches of hot mix asphalt pavement with 3 foot gravel shoulders.  The road will be open for travel with only minor delays expected.

County Road K

(County Road B – State Highway 77)

1.7 miles

Project consists of 2” hot mix overlay, placement of shoulder gravel, and pavement marking.

County Road CC

(Tiger Musky Road – Sandy Point Road)

1.33 miles

Project consists of 2” hot mix overlay, placement of shoulder gravel, and pavement marking.

County Road E

(Wilkie Road – County Road K)

1.93 miles

Project consists of 2” hot mix overlay, placement of shoulder gravel, and pavement marking.

County Road E

(Victory Heights Road – Jonan’s Road)

2.2 miles

Project consists of 2” hot mix overlay, placement of shoulder gravel, and pavement marking.


CTH NN

CTH NN at Worlds End Road

This project consists of replacing the three existing culvert pipes on CTH NN at Worlds End Road.  The existing culvert pipes are deteriorating and starting to fail.  The engineering firm, Cooper Engineering of Rice Lake, WI, has been contracted to perform the design and permitting of these culvert pipes.  The completion of this project is dependent on adequate funding remaining in the construction budget.  The project will necessitate closing of the roadway for two to three days.  A signed detour will be provided for the motoring public.